Oracle Sends Force Majeure Notice on New Mexico’s Project Jupiter but Says the Data Center Is on Schedule

Oracle wants room to put off rent if the 2.45-gigawatt campus misses its 2028 start because of power delays. Oracle and Blue Owl say nothing has changed, but the stock and the project's loans took a hit.
Oracle Sends Force Majeure Notice on New Mexico’s Project Jupiter but Says the Data Center Is on Schedule
Oracle Sends Force Majeure Notice on New Mexico’s Project Jupiter but Says the Data Center Is on Schedule

Update, Oct. 23: Oracle now puts Project Jupiter’s long-term economic impact for New Mexico at more than $13 billion, up from the $4.7 billion it cited in July, and says 4,393 people have worked on the site, according to a company release. The fuel-cell microgrid still has no air permit; on Oct. 15 Oracle and its power partner proposed an operating cap that would cut permitted emissions by about 35%.

Oracle has sent a force majeure notice to the developer of Project Jupiter, its giant data center campus in southern New Mexico, Bloomberg reported Thursday, citing people familiar with the matter. Oracle isn’t trying to walk away as the main tenant. It wants to be able to put off payments if the campus misses its planned 2028 start.

If both sides agree that a force majeure event tied to power commitments has happened, Oracle could get a three-year delay on rent once payments begin, one of Bloomberg’s sources said. Oracle would still cover other costs in the meantime and would owe rent for the full lease term. A person familiar with the matter told Reuters that securing power for the site is Oracle’s job under the contract, that Oracle can’t terminate the lease, and that Blue Owl has about $3 billion of equity in the project.

Both companies say the work is on track. “Force-majeure notices are commonplace in developments of this scale and are often used to preserve contractual rights among project partners,” Oracle spokesperson Michael Egbert wrote to the Albuquerque Journal. “They do not, by themselves, establish a project delay or change delivery expectations.” He added that the project “remains on our planned schedule.” Blue Owl, whose STACK Infrastructure unit is the developer, said the notice “does not change the financial commitments to this multiyear project.”

Investors were less calm. Oracle shares fell almost 5% early Thursday and closed down 3.47%, while Blue Owl dropped 3.6%, The Las Cruces New Mexican reported. Bloom Energy, which is supplying the site’s fuel cells, fell 3% and said on X that it remains committed to the contract, CNBC reported. About 20 banks lent $18 billion for the campus, and that debt is already trading below 90 cents on the dollar, according to Bloomberg, though the notice is not a default under the loan. Brokerage William Blair expects little near-term effect on Oracle, since Jupiter contributes no revenue in fiscal 2027.

The 1,400-acre campus near Santa Teresa, in Doña Ana County, is designed for 2.45 gigawatts and is part of Oracle’s computing deal with OpenAI under the Stargate build-out. Power is the sticking point. An Energy Transfer gas pipeline meant to start service in September was pushed back nearly six months to Feb. 1, 2027, after the New Mexico State Land Office repeatedly denied a proposed route. The Bloom fuel cells that would run on that gas still need a state air quality permit. Oracle says the fuel-cell design, which replaced the gas turbines and diesel generators in the original plan, cuts nitrogen oxide emissions by about 92%.

The New Mexico Supreme Court lifted stays on Sept. 17 that had paused the air permit case and blocked water pumping for construction. Opponents aren’t giving up. “It’s got to be unforeseeable … and this is completely foreseeable,” Mariel Nanasi, executive director of New Energy Economy, told The New Mexican, questioning whether force majeure applies at all.

Construction was 26% complete when Oracle executive vice president Mahesh Thiagarajan briefed county commissioners in September. Of 3,686 construction workers, 466, or nearly 13%, lived in the county, and union members made up 41% of the workforce, the Journal reported. In July, Oracle said the project had already produced nearly $80 million in tax revenue and had funded 80% of a $50 million commitment for local water infrastructure. It also backs an irrigation program with crop-data firm Arable that it expects to save about 21 million gallons of water a year.

Oracle’s push for the project has drawn its own scrutiny. After an investigation, the State Ethics Commission said Oracle registered and disclosed $3,444,500 spent on an advertising campaign aimed at winning the air permit, likely the largest lobbying ad campaign ever disclosed in the state.

Force majeure clauses are showing up more often in data center deals. “In AI data center projects, force majeure is no longer a back-end boilerplate provision,” law firm Quinn Emanuel Urquhart & Sullivan wrote in a June client alert cited by Bloomberg. “It is a core litigation and risk-allocation tool that can determine whether a delay remains isolated — or cascades through the project’s construction, customer, power, insurance, and financing documents.”

Subscribe for Updates

CloudPlatformPro Newsletter

The CloudPlatformPro Email Newsletter is the go-to resource for IT and cloud professionals. Perfect for tech leaders driving cloud adoption and digital transformation.

By signing up for our newsletter you agree to receive content related to ientry.com / webpronews.com and our affiliate partners. For additional information refer to our terms of service.

Notice an error?

Help us improve our content by reporting any issues you find.

Get the WebProNews newsletter delivered to your inbox

Get the free daily newsletter read by decision makers

Subscribe
Advertise with Us

Ready to get started?

Get our media kit

Advertise with Us